1. Testing, Commissioning, Operation & Maintenance of 81 MW Malakand-III Hydro Power Complex

All technical & support services being provided to the Client. More than two (200) hundred well experienced engineers & technical / support staff deployed in the power complex, for smooth, efficient & round the clock operation & maintenance of the complex. Most effective dealings with the power purchaser i.e. NTDC/WAPDA for power purchase agreement & energy payment invoices & NEPRA for tariff determination & indexation matters & other stake holders, on behalf of the Client. Initial term of Operation & Maintenance contract period being five (05) years which stands extendible with mutual consent.

Client

Sarhad Hydel Development Organization (SHYDO) Govt. of Khyber Pakhtunkhwa.

Performance

We have been able to recover the project capital cost of more than Five (05) Billion Pak Rupees, in thirty (30) months time period of commercial operation. The revenue on account of hydro power generation is invoiced to the Power Purchaser (NTDC/WAPDA) on monthly basis & payments timely received on our pursuance.

2. Operation & Maintenance of Shishi – Chitral Hydro Power Station

Based on our successful working at Malakand–III Hydro Power Complex, the Sarhad Hydel Development Organization (SHYDO) Govt. of Khyber Pakhtunkhwa has awarded us the Operation & Maintenance contract of 02 MW Hydro Power Station, at Shishi Chitral.

Client

Sarhad Hydel Development Organization (SHYDO) Govt. of Khyber Pakhtunkhwa.

Performance

We have been operating & maintaining the Power Station to the entire satisfaction of the Client.

B. DEVELOPMENT PROJECTS
1. 03 MW Sharda Hydro Power Project

In view of our well renowned expertise, the Govt of Azad Jammu & Kashmir (AJK) has awarded us the EPC Contract of developing 03 Mega Watt Sharda Hydro Power Project. The Penstock & all Electro-Mechanical Equipments of the project have since been delivered at site. We have fully mobilized to timely execute the project.

Client

Hydro Electric Board (HEB), Government of Azad Jammu & Kashmir (AJK).

Performance

The quality of Penstock & all Electro-Mechanical Equipments already factory tested & inspected by the Client engineers has been excellent and to the entire satisfaction of the Client’s. They are fully satisfied with our most professional working.

2. 03 MW Qadirabad Hydro Power Project

Being highly impressed with our methodical working, the Hydro Electric Board (HEB), Govt. of Azad Jamu & Kashmir (AJK) awarded us another EPC Contract of developing 03 MW Qadirabad Hydro Power Project. The Electro-Mechanical Equipments of the project have since been manufactured & factory tested/inspected by the Client’s Engineers. Again, they have appreciated the quality of the products being second to none. The E&M Equipments are delivered at site, followed by timely execution of the project.

Client

Hydro Electric Board (HEB), Government of Azad Jammu & Kashmir (AJK).

Performance

The Client has openly acknowledged our genuine expertise at every forum. They have rather placed us on our on top of there list.

Independent Power Producer (IPP)

The Government of Khyber Pakhtun khwa has very kindly allotted us a Hydro Power Site at Machai Canal, Dargai for developing 02 MW Hydro Power Project in private capacity. We are in the process of developing the project, to be completed by the end of year, 2011.

C. SERVICES
Client Services Division (CSD)

Hydro Tech Pak (Pvt.) Ltd. can provide Clients with highly competent technical manpower resources, to meet their specific and time bound requirements on long term as well as short term basis.

1. Consultancy Services

In addition to Operation, Maintenance & Development of Hydro Power Projects, we have recently entered into a joint venture with M/s Lahmeyer, leading Consultants from Germany, for working together thereby providing consultancy services for Hydro Power Projects, all over Pakistan.

2. Expertise

Our highly capable team of hydro power professionals, mostly WAPDA Ex-Chief Engineers, and most Senior Engineers very well know, how to deal with NEPRA for tariff determination & with Power Purchasers either regional distribution companies or NTDC of WAPDA. We are confident of delivering useful services to the Clients in all such fields. In fact, we have already been providing these expertise to a number of Clients, to their entire satisfaction.

3. Engineering and Services Division (ESD)

Hydro Tech Pak (Pvt.) Ltd. is fully equipped with the expertise for Design, Project Management, Construction Supervision, Testing, Commissioning, Operation and Maintenance of Power Projects. Based thereon, Hydro Tech Pak. (Pvt) Ltd. can enter into joint ventures with multinational companies for contracts on EPC basis.

4. Inventory Services Division (ISD)

Hydro Tech Pak (Pvt.) Ltd. can facilitate the Power Projects in Pakistan, by arranging / importing Spares / Stores at most competitive prices for their smooth, efficient and reliable (O&M), from all over the world.